Crews are working on the subway station entrance and exit at Wilshire/La Brea. (photo by Edwin Folven)
Metro is holding a webinar on D Line subway project construction on Wednesday, Feb. 5, at noon. The webinar will provide updates on all three segments of the project along Wilshire Boulevard from Wilshire/Western to the Westwood/VA Hospital station. The webinar will include information on construction timelines, project milestones and how the new stations will improve transit access from downtown to the westside.
To participate, visit zoom.us/j/96626476708 and use the webinar ID: 966 2647 6708. To participate by phone, call (213)338-8477.
Plans call for a phased opening of the D Line extension. Section one from Wilshire/Western to Wilshire/La Cienega is anticipated to open in late 2025. Section two from Wilshire/La Cienega to the Century City/Constellation station is anticipated to open in 2026 and section three to the Westwood/VA Hospital station is expected to open in 2027. Work is currently ongoing on all three sections.
At the eastern end of the project, crews are restoring streets and sidewalks and are working underground on the subway stations. Through January 2025, Wilshire Boulevard will be reduced to two lanes in each direction between Oxford Avenue and St. Andrews Place. Left turns are prohibited from westbound and eastbound Wilshire Boulevard to Western Avenue and from eastbound Wilshire Boulevard to northbound St. Andrews Place. The traffic pattern supports civil restoration near the Wilshire/Western staging yard.
At the Wilshire/La Brea and Wilshire/Fairfax stations, crews are repairing streets and sidewalks within K-rail work zones. Lane closures on Wilshire Boulevard may be in place near the stations. Through March, Wilshire Boulevard is reduced to two lanes in each direction at La Jolla Avenue, where a K-rail enclosure is in place on the west side of the Wilshire/La Jolla intersection.
Lane closures are also in place near the Wilshire/La Cienega subway station, between San Vicente and La Cienega boulevards. A K-rail work zone remains in place along the north side of Wilshire Boulevard. Intermittent single-lane bump outs may be utilized on Wilshire and La Cienega boulevards.
At the Wilshire/Rodeo station, Metro will start piling and potholing activities in preparation for construction of appendage structures for the future station. Work will take place in multiple stages during daytime hours along Wilshire Boulevard, between Cañon and Beverly drives. The work involves the closure of a single curb lane on Wilshire Boulevard to install piles around the station box perimeter.
The work will occur from just west of the Wilshire/Beverly intersection to a location just west of Crescent Drive. Piling involves drilling holes up to 30 feet deep using a rig, placing steel beams into each hole with a crane and backfilling the holes with concrete. The work requires temporary curb lane closures on Wilshire Boulevard.
Station construction and concrete placement is ongoing at the Century City/Constellation station.
Placement of structural concrete for the station is substantially complete, and construction of the interior and roof structures is ongoing 24 hours beneath Constellation Boulevard. Traffic lane closures are in place on Constellation Boulevard to support daytime station construction and material deliveries. Eastbound and westbound vehicle access on Constellation Boulevard is being maintained between Century Park West and Century Park East.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.