Crews are working in Beverly Hills on the Beverly Drive Station. (photo by Edwin Folven)
Construction is ongoing near Wilshire Boulevard and Beverly Drive on the D Line Extension Project.
The first segment of the D Line subway extension opened in May to Wilshire/La Cienega. The second segment, which includes the Beverly Drive and Century City stations, is anticipated to open in spring 2027. The third segment to the Westwood/VA Hospital is scheduled to open in fall 2027.
Metro is holding a construction update meeting on the Beverly Hills stations on Sept. 9 from 6-7 p.m. at Beverly Hills City Hall, 455 N. Rexford Drive. Admission is free. To register, visit metro.net/projects/westside.
Crews are working at street level and underground on the Beverly Drive Station. Through Friday, Sep. 25, sidewalk restoration is ongoing near Sterling Plaza. The work is being conducted on Wilshire Boulevard between North Beverly Drive and the alley driveway west of Cañon Drive. Work hours are 7 a.m.-4:30 p.m. (9 a.m.-4:30 p.m. for noise generating work) and 8:15 p.m.-7 a.m.
Intermittent lane reductions for westbound Wilshire Boule-vard and sidewalk closures in front of Sterling Plaza will be implemented at the corner of Wilshire Boulevard and Beverly Drive. Flaggers will help guide pedestrians through the temporary detour. Complete sidewalk restoration is expected by Sept. 25.
Work is also ongoing behind K-rail enclosures along Wilshire Boulevard between Beverly and Crescent drives. Two lanes will be maintained in each direction along Wilshire Boulevard. Sidewalks may be intermittently closed in the area.
Construction at the Century City Station also continues in September. Work will continue on appendages, which are underground rooms and passageways adjacent to the main station. Potholing continues on the northwest side of Constellation Boulevard near Avenue of the Stars. Traffic lane reductions will be implemented and temporary sidewalk closures and single-lane traffic operations with flagging may be in place intermittently on Constellation Boulevard.
Construction is also ongoing at the UCLA/Westwood Station, requiring a closure of eastbound lanes on Wilshire Boulevard. Through Oct. 2, crews are completing drilling for an elevator casing at the southeast entrance. Eastbound Wilshire Boulevard will be closed between Gayley Avenue and Westwood Boulevard. Work hours are Monday through Friday from 9 p.m.-6 a.m.; and Saturday and Sunday from 6 a.m.-3 p.m. All westbound lanes will remain open. Eastbound traffic will be diverted to Santa Monica Boulevard via Sepulveda Boulevard or Veteran Avenue, and back to Wilshire Boulevard via Westwood Boulevard.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net or visit metro.net.









0 Comment