Crews are constructing the Beverly Drive Station in Beverly Hills, working underground and at street level. (photo by Edwin Folven)
The D Line subway has reopened between the Wilshire/La Cienega and Union Station after a closure in late October to install permanent electrical equipment and conduct maintenance. The Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega stations are open.
Farther west, crews are constructing the Beverly Drive Station in Beverly Hills, working underground and at street level. Through Nov. 20, final street restoration, paving and restriping work is ongoing between Rexford and El Camino drives. Crews are also installing ADA ramps at street corners near the new subway station.
Work hours are 8:15 p.m.-7 a.m. Lane reductions will occur along Wilshire Boulevard during the work.
Work continues on the Century City Station in November behind K-rail enclosures. Crews are building appendage structures, which are underground rooms and passageways adjacent to the main station. Construction is ongoing within current traffic closures around the station area. Backfill operations above the final concrete structure for the station continue in November, requiring intermittent nighttime closures coordinated with ongoing concrete placement.
Crews are concurrently working on the station entrances at the Westwood/UCLA Station in UCLA Lot 36. The work may require temporary lane closures to access the site. Closures may impact westbound Wilshire Boulevard between Westwood Boulevard and Veteran Avenue, as well as crosswalks on Wilshire Boulevard and Gayley Avenue, and southbound right turn pockets at Gayley/Wilshire and Westwood/Wilshire.
Near the Westwood/VA Hospital Station, motorists are advised about upcoming nightly closures on the southbound 405 Freeway onramp and offramp to eastbound Wilshire Boulevard from Nov. 5-9. A ramp closure for work preparation is planned on Thursday, Nov. 5, from 10 p.m.-5 a.m. Freeway traffic will be diverted to Santa Monica and Sunset boulevards. The curb lane of eastbound Wilshire Boulevard west of the southbound 405 onramp will be closed, and the eastbound onramp will be closed from Bonsall Avenue to Wilshire Boulevard.
Following the Nov. 5 closure, a 55-hour weekend full closure of the southbound 405 onramp and offramp to eastbound Wilshire Boulevard runs from 10 p.m. on Friday, Nov. 6 through 5 a.m. Monday, Nov. 9. A second weekend closure is reserved as a contingency from Friday, Nov. 13, through Monday, Nov. 16.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net or visit metro.net.