A Los Angeles County Superior Court judge denied challenges to environmental exemptions for Phase 1 of the Fountain Avenue Streetscape Project. (photo courtesy of the city of West Hollywood)
A Los Angeles County Superior Court judge denied legal challenges to the city of West Hollywood’s Fountain Avenue Streetscape Project on Monday, Nov. 2.
Judge Richard L. Fruin ruled that Phase 1 of the Fountain Avenue Streetscape Project is exempt from environmental review under the California Environmental Quality Act and denied a petition for writ of mandate filed by Michael J. Kilroy on Oct. 29, 2025.
Kilroy, who owns an eight-unit apartment building at 1308 N. Flores St., near the intersection of Flores Street and Fountain Avenue, argued that the city improperly relied on CEQA exemptions. He said the project should not be exempt because reducing traffic lanes could cause “increased vehicle emissions from traffic delays and diversions,” according to the petition for writ of mandate obtained by the Beverly Press.
“The project involves the removal of two traffic lanes on Fountain Avenue for conversion to bike lanes, resulting in significant parking loss, traffic diversion and potential environmental impacts,” Kilroy said in the petition for writ of mandate. “The city’s failure to conduct environmental review constitutes a prejudicial abuse of discretion.”
The West Hollywood City Council approved Phase 1 of the Fountain Streetscape Project on Sept. 15, 2025, by a 3-2 vote. Councilmembers Chelsea Byers, John Erickson and Danny Hang voted in favor; Councilmembers John Heilman and Lauren Meister opposed. Phase 1 will include protected bike lanes, high-visibility crosswalks, painted curb extensions on side streets, self-watering planters within some curb extensions, a new street layout with one vehicle lane in each direction, curbside street parking on the south side only, repaving of the entire street and publicly visible bicycle counters.
After construction is complete, approximately 210 parking spots will be removed from the area, and curbside street parking will only be available on the south side of the street, alongside the bike path. The project also includes removing one traffic lane in each direction to make space for the bike path.
The court said Kilroy did not prove a “significant environmental effect” to support an exception, according to court documents. The court found that the City Council’s decision to forfeit environmental review for Phase 1 was legal.
Under the law, CEQA exempts “pedestrian and bicycle facilities that improve safety, access or mobility including new facilities within the public right of way.” CEQA guidelines also allow exemptions for “the addition of bicycle facilities, including but not limited to … bicycle lanes.”
According to the city, the project is meant to improve pedestrian and bicycle safety on Fountain Avenue and encourage drivers to slow down. Between 2021 and 2026, 16 pedestrian crashes were reported on Fountain Avenue, including two serious or fatal crashes, according to Safe Streets Map. Most recently, 27-year-old Blake Ackerman died after a hit-and-run collision in July on Fountain Avenue.
Ackerman’s family is suing the city of West Hollywood for “improper upkeep or maintenance of Fountain Avenue,” Erickson said at the Oct. 19 West Hollywood City Council meeting.
This is not the first time the Fountain Avenue Streetscape Project has drawn fire from West Hollywood residents. Since approving it in 2025, the West Hollywood City Council has discussed the controversial project several times.
During the Oct. 19 West Hollywood City Council meeting, Meister proposed scaling back planned safety improvements to Fountain Avenue, but the motion failed 3-2. Byers, Erickson and Hang voted in favor; Heilman and Meister opposed.
If passed, the motion would have directed staff to evaluate an alternative design for Fountain Avenue that would remove the protected bike lane from the project, maintain the road’s current parking capacity, reduce the road to one travel lane in each direction and add a center turn lane.
The project will be implemented in two phases. Phase 1 is the initial roadway reconfiguration, while Phase 2 is a full reconstruction of Fountain Avenue to bring the curb ramps and sidewalks into ADA compliance. Preliminary plans for Phase 2 include upgrading curb ramps to comply with ADA standards, widening sidewalks where feasible, improving landscaping, changing traffic signals and relocating both underground and overhead utilities to accommodate a new neighborhood-oriented street design.