Crews are restoring curbs and gutters near the Wilshire/La Cienega subway station. (photo by Edwin Folven)
Construction is nearly complete along the first segment of the D Line subway extension project, which will open on May 8 between Wilshire/Western and Wilshire/La Cienega.
Crews are restoring streets and sidewalks around the Wilshire/La Cienega station, with recent work including completion of station plazas, sidewalks and landscaping along Wilshire Boulevard. In addition to the Wilshire/La Cienega station, the first segment of the project includes subway stations at Wilshire/La Brea and Wilshire/Fairfax.
Civil restoration continues on the north and south sides of Wilshire Boulevard between Stanley Drive and San Vicente Boulevard, including the replacement of curb ramps at Stanley/Wilshire and Le Doux/Wilshire. Wilshire Boulevard may be reduced to two lanes around work sites.
Crews are also repairing sidewalks and curbs on the southeast corner of Wilshire/La Cienega. Northbound La Cienega Boulevard may be reduced to two lanes near Wilshire Boulevard for curb, gutter and ramp replacement, and traffic signal system installation.
Wilshire and La Cienega boulevards and segments of adjoining side streets will be repaved this summer, with dates to be announced. The repaving, which will occur over a series of weekends, requires temporary street closures.
The second segment of the D Line subway extension project runs between Wilshire/ La Cienega and the Century City stations and includes the Beverly Drive Station in Beverly Hills. Work is ongoing on the second segment, which is scheduled to open in spring 2027.
A construction zone remains in place at the subway station along Wilshire Boulevard between Beverly and Crescent drives. Through June 26, crews are completing curb, gutter, underground electrical and sidewalk restoration work along the south side of Wilshire Boulevard between South Cañon Drive and Reeves Drive. Sidewalk closures will be implemented around the work zones. Pedestrian access to 9420 Wilshire Blvd. will be maintained behind K-rail safety barriers adjacent to the existing sidewalk.
In Century City, crews are working at and around the subway station near Constellation Boulevard and Avenue of the Stars. Through Sunday, May 10, temporary pedestrian sidewalk closures will be implemented during phase four of deck removal. The east sidewalk along Avenue of the Stars, just north of Constellation Boulevard, will be closed during the work. The south sidewalk along Constellation Boulevard, just west of Avenue of the Stars to Solar Way, will also be closed. Pedestrian crosswalk access at the intersection of Constellation Boulevard and Avenue of the Stars will be maintained, except for the north-south crosswalk on the west side of Avenue of the Stars. North-south pedestrian access will be maintained on the west crosswalk of Constellation Boulevard and Solar Way.
Construction is also ongoing in Westwood on the third and final segment of the D Line extension project. The third segment has stations at Westwood/UCLA in UCLA Lot 36, and the VA Hospital. Hauling, utility removal, material delivery, concrete pours and backfilling excavations continue through June 30. Closures may impact westbound Wilshire Boulevard between Westwood Boulevard and Veteran Avenue.
Work on the Westwood/VA Hospital Station is ongoing in Lot 42 at the VA campus and a staging yard west of Bonsall Avenue.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net or visit metro.net.