A stretch of Wilshire Boulevard between Western Avenue and St. Andrews Place will be closed for final repaving on Aug. 1-4 as part of the D Line extension project. (photo by Edwin Folven)
The Los Angeles County Metropolitan Transportation Authority is holding a virtual meeting on Thursday, July 24, at 6 p.m. with information about paving work planned on Aug. 1-4 at Wilshire/Western.
Wilshire Boulevard will be closed between Western Avenue and St. Andrews Place from 9 p.m. on Friday, Aug. 1, through 6 a.m. on Monday, Aug. 4. The closure will support final paving work west of the Wilshire/Western intersection. A detour route will be in place and local access will be maintained between Wilton Place and St. Andrews Place. Motorists are encouraged to use Crenshaw Boulevard and Western Avenue to Olympic Boulevard to bypass the closure. For information and to join the online meeting, visit eventbrite.com/e/d-line-section-1-2-lunch-with-us-webinar-beverly-hills-stations-tickets-1329173667219.
The existing and new D Line subway lines are being connected east of the Wilshire/Western station. The segment of the existing D Line between Wilshire/Western and Wilshire/Vermont is closed through July 25. Bus Shuttle 855 and Metro Lines 720 and 20 provide service on Wilshire Boulevard between the Wilshire/Western and Wilshire/ Vermont stations.
Street restoration work is also ongoing around the Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega stations and lane closures are in place near the intersections. Crews are building the station entrances and exits above ground in staging areas and are working underground on the stations and tunnels.
Beginning the weekend of July 26-27 and continuing for approximately four months, a K-rail work zone will be implemented on the south side of Wilshire Boulevard between San Vicente and La Cienega boulevards. The traffic control will support ongoing restoration work including new curbs, sidewalks, pedestrian ramps and tree wells. Two lanes will remain open in each direction on Wilshire Boulevard and a five-foot pedestrian walkway will be maintained along the south side of the street. The eastern sidewalks on North Gale Drive and North La Cienega Boulevard will also be closed through July 26 to support concrete pouring.
Work is ongoing at the Wilshire/Rodeo station. A full sidewalk closure is planned on the north side of Wilshire Boulevard between Beverly and El Camino drives on July 26-27 as crews conduct piling activities for appendage structures adjacent to the station.
Crews are also completing the final tie-ins on a new waterline near the Wilshire/Rodeo station through July 25. The work will be performed at night during off peak hours to minimize impact. Notices will be issued prior to water service interruption.
At the Century City/ Constellation station, crews are preparing to remove deck panels and restore the street along Constellation Boulevard between Century Park East and Solar Way. Through Aug. 15, temporary traffic control will be in place to support LADWP water and power utility installation for the subway station. Lane reductions and closures may be in place during day and night non-peak traffic periods.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.