A full closure of Reeves Drive is planned south of Wilshire Boulevard for work on the Wilshire/Rodeo station. (photo by Edwin Folven)
Work on the D Line subway extension is ongoing in late February, with crews working at multiple locations along Wilshire Boulevard in Wilshire Center, the Miracle Mile, Beverly Hills and Century City.
Through at least March, street restoration work is ongoing near Wilshire/Western. Wilshire Boulevard is reduced to two lanes in each direction between Oxford Avenue and St. Andrews Place, and left turns are prohibited from Wilshire Boulevard to Western Avenue and from eastbound Wilshire Boulevard to northbound St. Andrews Place.
Near the Wilshire/La Brea subway station, lanes may be closed through March along Wilshire Boulevard between Sycamore Avenue and Detroit Street, and on La Brea Avenue between Sixth and Eighth streets. The lane closures support street restoration in the area. Cross passage work between the tunnels is also ongoing in the Miracle Mile, where a K-rail work zone is in place through March on Wilshire Boulevard between Courtyard Place and Masselin Avenue.
A K-rail work zone is located in the middle lanes of Wilshire Boulevard between Fairfax and Spaulding Avenue through March. Wilshire Boulevard is reduced to two lanes in each direction near the intersection. Crosswalks along Wilshire Boulevard will be maintained at Spaulding Avenue, Ogden Drive and Fairfax Avenue. A K-rail work zone is also in place in the center of the Wilshire/La Jolla intersection, where Wilshire Boulevard is reduced to two lanes in each direction.
At Wilshire/La Cienega, a K-rail work zone has been implemented along the north side of Wilshire Boulevard between San Vicente and La Cienega boulevards. Two lanes in each direction are open on Wilshire Boulevard between San Vicente and La Cienega boulevards. Instrumentation and utility work, street maintenance, strut removal and concrete and material deliveries are ongoing at and around the Wilshire/La Cienega station.
Work is ongoing near the Wilshire/Rodeo station. As early as Feb. 24, a full closure of South Reeves Drive will be implemented from the Wilshire Boulevard crosswalk to an alley just south of Wilshire Boulevard. The closure supports the removal of the temporary decking system, station entrance structure construction and Reeves Drive street restoration. The work is expected to last six weeks.
The Beverly Hills City Council approved a three-week full closure of Wilshire Boulevard between El Camino and Crescent drives. Deck removal preparation work has begun along Wilshire Boulevard in advance of the March 17 three-week full closure.
Placement of structural concrete for the Century City/Constellation station is substantially complete and construction of the interior and roof structures is ongoing. Partial traffic lane closures are in place on Constellation Boulevard. Eastbound and westbound vehicle access on Constellation Boulevard is open between Century Park West and Century Park East. All driveways are accessible in the area.
For questions and concerns about the D Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.