The north portal would have been located at the northwest corner of Wilshire Boulevard and Beverly Drive. (photo by Tabor Brewster)
The Beverly Hills City Council unanimously voted to discontinue the north portal Metro station project in a meeting on May 7. The decision comes after the estimated overall cost for the project – which would have placed a second entrance for the Wilshire/Rodeo Metro station at the northwest corner of Wilshire Boulevard and Beverly Drive – increased from $78.5 million to $134.2 million. According to city staff, the increase in estimated overall cost was due to limited supplies, increased transportation costs and a shortage of skilled labor.
In November 2020, the city and Metro agreed to develop an additional entrance to the Wilshire/Rodeo station and split the cost in half as part of a settlement agreement. The city had threatened litigation against Metro and the Federal Transit Administration, alleging that the two entities did not adequately address issues brought on by the station in an environmental impact statement. Many residents and city leaders expressed concern in 2020 over the location of the singular main portal at the southwest corner of Wilshire Boulevard and South Reeves Drive and the impact it would have on the surrounding area. The north portal was meant to remedy some of the issues by providing an additional entrance and exit to the station. The city agreed to pay half of the project – $39.25 million. However, the increase in cost would have required the city to pay over $67 million if it were to continue with the project, a price deemed too high by the City Council on May 7.
“It still astounds me that when designing this that [Metro] would put the main portal on the south side when all the businesses are on the north. It just didn’t make any sense, and I think from that point forward we can all assume that their design decisions are not the greatest,” Beverly Hills Mayor Lester Friedman said. “One of the design decisions was the tunnel leading from the main subway box to the potential north portal … 170 feet of prime real estate for people to camp out in. So I’m not sad to see this go away. I’m upset that there’s not a north portal – that’s where it should’ve been in the first place. But based on the cost and based on the potential difficulties with that tunnel, I am supportive of the three recommendations.”
The City Council voted 4-1 in November 2020 to approve the settlement agreement with Metro. Councilman John Mirisch was the one vote in opposition. At the time, Mirisch cited concerns over cost and poor design and argued that Metro should be responsible for the entire project instead of half. Mirisch echoed his initial concerns and called the agreement a “bad deal” that was poorly negotiated in the May 7 meeting.
“I hate to say I told you so, but I told you so,” Mirisch said.
Per the settlement agreement, the city is now required to meet with Metro to determine the future of the north portal project.
“At this time, Metro will continue to complete construction of the D Line Subway extension project. The station is being constructed between Beverly Drive and Crescent Drive with the necessary infrastructure inside the station box to connect to a future north portal if the city chooses to advance the project in the future,” Metro communications director Dave Sotero said.
According to Sotero, Metro had already begun work inside the station box to accommodate the north portal, and the city will have to split the cost of the work completed so far.
“Metro has spent less than $10 million on the north portal project. Our settlement agreement with the city of Beverly Hills requires a 50/50 sharing of costs spent to date,” he added.