Lane closures are occurring as crews work on the subway station in Beverly Hills near Wilshire Boulevard and Beverly and Cañon drives. (photo by Edwin Folven)
Construction continues on the Metro D Line subway extension project in the Greater Wilshire, Miracle Mile, Beverly Hills, Century City and Westwood areas.
Section one of the project, which includes the Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega stations, and section two, which includes the Wilshire/Rodeo and Century City/Constellation stations, are scheduled to open in 2025. Section three, which includes the Westwood/UCLA and Westwood/VA Hospital stations, is anticipated to open in 2027.
Beginning the weekend of March 1 and continuing for four consecutive weekends (including two contingency weekends), workers will remove concrete deck panels on Wilshire Boulevard between Western Avenue and Manhattan Place. Work will begin at 9 p.m. on Friday and continue through 6 a.m. on Monday. Wilshire Boulevard will be closed to traffic between Western Avenue and Manhattan Place. Southbound traffic on Manhattan Place will be maintained onto Wilshire Boulevard, with drivers detoured to westbound Wilshire Boulevard. East-west pedestrian traffic will be prohibited between Western Avenue and Manhattan Place on the north side of Wilshire. A pedestrian detour will be open on the south side of Wilshire Boulevard.
Crews will be completing street restoration work near the Wilshire/La Brea station through the end of March. Wilshire Boulevard will be reduced to two lanes in each direction between Highland and La Brea avenues. Intermittent closures will also be implemented on Detroit Street at Wilshire Boulevard through March 31.
Work is also ongoing at the Wilshire/Fairfax station. North-bound Orange Grove Avenue will be closed south of Wilshire Boulevard for station construction. Wilshire will also be reduced to two lanes in each direction at La Jolla Avenue through June, and left turns from eastbound Wilshire Boulevard to northbound La Jolla Avenue will be restricted. A K-rail enclosure will remain in place on the west side of the Wilshire/La Jolla intersection for cross passage construction between the subway tunnels.
Street restoration will continue through April near Wilshire/La Cienega. A K-rail work zone has been implemented on the north side of Wilshire Boulevard, and two lanes are open in each direction between San Vicente and La Cienega boulevards. Intermittent single-lane bump outs may be utilized on Wilshire and La Cienega boulevards.
Piling work and excavation is ongoing in the area.
Crews are building passageways and rooms known as appendages next to the Wilshire/Rodeo station near Wilshire Boulevard and Cañon and Beverly drives. Excavation activities have been completed on South Beverly Drive and appendage construction will continue through February. The work requires nightly lane closures in both directions from 8 p.m.-7 a.m. A full closure of South Cañon Drive from Wilshire Boulevard is anticipated to be in place through the first week of April. The alley south of Wilshire Boulevard will remain accessible from northbound Cañon Drive.
Work is also ongoing on the Century City/Constellation Station. Utility work continues to progress as crews relocate a sewer and storm drain from within the project area. The closure on Avenue of the Stars may be extended through May 2024. Left turns are restricted from northbound Avenue of the Stars onto westbound Constellation Boulevard, and Avenue of the Stars will be reduced to one lane north and southbound at Constellation Boulevard. Lane closures will be required overnight on Avenue of the Stars.
For questions and concerns about the Purple Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.