Crews are working 24 hours in the construction staging yard near Wilshire/La Cienega. (photo by Edwin Folven)
Metro is reminding the public about decking removal that will cause full closures of Wilshire Boulevard at La Brea Avenue beginning the weekend of Sept. 29, and continuing for six weekends.
The work is part of the Purple Line Extension subway project. Concrete temporary deck panels will be removed on the surface of Wilshire Boulevard between La Brea Avenue and Detroit Street and replaced with a permanent surface. Each weekend, the work will begin on Friday at 9 p.m. and continue through 6 a.m. the following Monday. Wilshire Boulevard will be closed to through traffic between Mansfield and Cloverdale avenues during the work. La Brea Avenue will also be closed in both directions at Wilshire Boulevard.
Olympic Boulevard and Sixth Street are recommended as detours. Signs indicating detour routes will be in place during the closures. Local access to Wilshire Boulevard will be maintained at Mansfield and Citrus avenues.
Metro is also working at many other locations along the Purple Line Extension project. Work on the Wilshire/Fairfax station is ongoing underground in the staging area near Wilshire Boulevard and Ogden Drive, and at street level. A K-rail work zone on the north side of Wilshire Boulevard near Fairfax Avenue will be in place through November. Wilshire Boulevard has been reduced to two lanes in each direction between Spaulding Avenue and San Diego Way. Wilshire Boulevard will also be reduced to two lanes in each direction at La Jolla Avenue through June 2024.
Near Wilshire/La Cienega, station appendage construction is ongoing along Wilshire Boulevard between San Vicente and La Cienega boulevards. Wilshire Boulevard has been reduced to two lanes in each direction in the area and left turns are restricted at Gale and Hamilton drives. Instrumentation work, utility work and street maintenance are also ongoing at Wilshire/La Cienega.
Excavation activity is ongoing on South Beverly Drive in September and is anticipated to require nightly lane closures in both directions from 8 p.m. to 7 a.m. Piling and decking activity is scheduled to begin at the end of September on South Cañon Drive at Wilshire Boulevard and will require weekend closures. South Cañon Drive will be closed from 8:15 p.m. on Fridays through 7 a.m. on Mondays.
Utility work also continues near Wilshire/Rodeo, where Southern California Edison is installing permanent power feeds to the station. Crews are conducting station appendage potholing in preparation for construction of rooms and passageways adjacent to the underground station. Deliveries of material, equipment and concrete will occur daily near Wilshire/Rodeo.
At the Century City/ Constellation station, a sewer and storm drain are being relocated from the station site. Initial concrete pours for the base invert level of the station have begun. Work on side structures adjacent to the future station is also underway.
Metro is advising about traffic closures in the area. Partial traffic lane closures on Constellation Boulevard facilitate work at the station. Vehicle access on Constellation Boulevard is being maintained between Century Park West and Century Park East. All driveways are accessible in the area.
For questions and concerns about the Purple Line Extension project, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.