Construction firm Fonder-Salari expects to save $23 million by following a new plan for the construction of Beverly Hills High School athletics facilities. (photo by Edwin Folven)
During a June 27 Beverly Hills Unified School District study session, developers with Fonder-Salari, the construction firm overseeing the district’s bond-funded construction projects, presented a revised plan for the construction of new athletic facilities at Beverly Hills High School.
Fonder-Salari CEO Amin Salari estimated that the revised plans would save the district approximately $23 million, as compared to the previous master plan. Salari said his team realized that they could use the gradual elevation of the athletics area to their advantage by reducing the amount of earth removal required, and use those funds to build facilities instead.
Salari said he expects to save $8 million by scrapping plans to build underground parking and instead build two levels of above-ground parking. Under the new plan, the parking areas will be adjacent Heath Road, while the original plan established a parking area underneath the future Building C.
A start date for construction of Building C, which will replace the Konheim Building as the school’s main athletics building, has not been established. However, Salari estimated Building C’s construction would take approximately two years.
The revised plan also eliminates plans to construct new retaining walls and reduce the size of existing ones, which would have cost more than $5 million, Salari said.
Salari cited an additional $9.328 million in savings from foregoing plans to construct a new restroom, storage buildings, football and baseball bleachers, and associated earth removal.
The board members were unanimously supportive of the revised plan.
“I know that you came into a project that didn’t have a lot of information, and it’s taken a long time to even just find the information that you needed so that you could assess the situation,” board member Mary Wells said. “And then to go out and rebid or to come up with these new numbers and then go out and find how we could do it in a better way so that it would be possible for us to get here, it’s really amazing.”
The district’s construction projects are funded by Measure E, a $334 million bond approved by voters in November 2008, and the $385 million Measure BH bond approved in 2018. Construction has been slow, and in July 2022, Fonder-Salari was selected to oversee the taxpayer funded projects.