Work on the future Wilshire/Fairfax subway station is occurring in a staging yard on the south side of Wilshire Boulevard. (photo by Edwin Folven)
Metro has announced that no construction will occur on the Purple Line Extension project on Christmas and New Year’s Day, and work will also be suspended in the city of Beverly Hills on Christmas Eve.
The public can stay up to date with the latest information on subway work in 2021 during the next lunchtime webinar on Wednesday, Jan. 13, from noon to 1 p.m., via Zoom. The webinar will include updates on sections of the project running from Wilshire/Western to Century City, including portions in the city of Beverly Hills. To join, call (888)788-0099, and use the ID: 955 7708 4809.
Work continues at many locations along the route, including at the future Wilshire/Rodeo and Wilshire/La Cienega subway stations in Beverly Hills. At Wilshire/Rodeo, crews are anticipated to reach a final depth of 100 feet during the first quarter of 2021. New hauling hours for removing soil have been announced. From 10 a.m. to 4 p.m., two lanes will be open in each direction on Wilshire Boulevard between El Camino and Crescent Drive to accommodate soil removal from the Reeves staging yard. From 10 p.m. to 10 a.m., Wilshire Boulevard will be reduced to one lane in each direction between El Camino and Crescent drives, when excavation will occur through deck openings along Wilshire Boulevard at Canon Dive, and just west of Beverly Drive. Ground monitoring instruments are also being installed along the tunnel alignment and around the Wilshire/Rodeo station. New work hours are weekdays from 7 a.m. to 4 p.m. and weekends from 8 a.m. to 7 p.m. for work on Wilshire Boulevard, and weekdays from 8 a.m. to 6 p.m. in the neighborhoods surrounding Wilshire Boulevard.
Station construction and material deliveries continue at Wilshire/La Cienega and ongoing concrete and material deliveries to the Wilshire/La Cienega station box are anticipated to continue this week. Eastbound Wilshire Boulevard may be intermittently reduced to one lane, and westbound Wilshire Boulevard may be reduced to two lanes between Gale and Hamilton drives. Gale Drive will also be intermittently closed at Wilshire Boulevard to support construction in the Gale staging yard.
A K-rail enclosure in the center lanes at Wilshire/San Vicente is anticipated to be in place through at least the first two weeks of the new year to support ongoing tunnel and mitigation work underneath Wilshire Boulevard. Southbound San Vicente Boulevard will be closed at Wilshire Boulevard on weekends beginning Jan. 9. One lane from southbound San Vicente to westbound Wilshire Boulevard will be open. A detour will be in place.
Station construction, hauling and concrete pouring are ongoing near Wilshire/Fairfax. Wilshire Boulevard will be reduced to two lanes in each direction between San Diego Way and Spaulding Avenue through next August. Intermittent lane closures may be in place to support deck panel maintenance and investigation.
A K-rail work zone has been installed at the southwest corner of Wilshire Boulevard and Fairfax Avenue to support work on appendages to the main subway tunnels. Orange Grove Avenue remains closed south of Wilshire Boulevard until January. Ogden Drive will be closed intermittently Monday through Saturday at Wilshire Boulevard.
At Wilshire/La Brea, hauling, deliveries and tunneling support are ongoing in construction staging yards and from a K-rail enclosure at Wilshire Boulevard and Orange Drive. Intermittent lane closures on Wilshire Boulevard and side streets between Highland Avenue and Detroit Street may be in place to support construction from 6 a.m. to 4 p.m., Monday through Friday. Orange Drive will remain closed north of Wilshire Boulevard through the end of February.
A work zone on the west side of the intersection of Wilshire and Rimpau boulevards is anticipated to be in place through next May. Wilshire Boulevard has been reduced to two lanes in each direction between June Street and Muirfield Road. Concrete and material deliveries are anticipated to continue at the site.
A K-rail enclosure at Wilshire and Plymouth boulevards will be in place for approximately one year. Wilshire Boulevard will be reduced to two lanes in each direction between Windsor and Plymouth boulevards. Work will occur 24 hours in the enclosure.
Tunneling support and construction continue in a staging yard near Wilshire Boulevard and Manhattan Place near the Wilshire/Western station. Northbound Manhattan Place will be intermittently closed just north of Wilshire Boulevard from 4 a.m. to midnight, Monday through Friday, and 8 a.m. to 11 p.m., Saturday. Intermittent single lane closures on Wilshire Boulevard may be necessary between Western Avenue and Manhattan Place. Access to businesses will be maintained and a signed pedestrian detour has been installed.
For questions and concerns, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net, or visit metro.net.