Approved by the city of West Hollywood in 2015, the 8899 Beverly project is estimated to be completed in September. (photo by Morgan Keith)
Pankow Builders will be hosting a community forum tonight, Jan. 16, to discuss construction progress on the 8899 Beverly project and what residents, business owners and other stakeholders can expect as completion nears. Attendees are asked to meet at 5 p.m. at the construction gate at 8915 Beverly Blvd.
The developer will provide information on the upcoming tower crane removal and completion of Rosewood Avenue utility work. Additionally, the general contractor responsible for the project’s townhome construction on Rosewood Avenue will be introduced.
Lane closures on Beverly Boulevard will be implemented as crews begin disassembling the tower crane on Feb. 28, according to John Hernandez, a Pankow Builders spokesman. Additional lane closures will be necessary over the coming months until the project’s estimated completion in September.
“[Pankow has] been very good at updating the neighborhood, specifically Rosewood [Avenue] on how they’re doing on the project,” said Manny Rodriguez, vice president of the West Hollywood West Residents Association. “We’re happy about them keeping the flow of information coming.”
Construction began on the 10-story building after the project was approved by the city of West Hollywood in 2015. Proposed by Beverly Hills-based real estate investment firm Townscape Partners, the project will include 40 condominiums, 15 apartments reserved for very low- and moderate-income households and eight townhomes along Rosewood Avenue.
None of the rooms have been placed on the market, although a list for prospective buyers has been created by Townscape Partners on its website.












0 Comment