Crews at Wilshire/Western recently welcomed the tunneling machines digging the Purple Line Extension project’s subway tunnels. The boring machines are currently being disassembled and returned to the Wilshire/ La Brea staging area, where they will be reassembled and will start tunneling toward Beverly Hills. (photo courtesy of Metro)
Metro is providing information on construction occurring along the Purple Line Extension subway project route from Wilshire Boulevard and Western Avenue, to Century City.
Excavation, concrete and street maintenance work is ongoing near Wilshire/Western. Single lane closures will occur intermittently between Western Avenue and Manhattan Place from 9 a.m. to 3:30 p.m., Monday through Friday. Northbound Manhattan Place will be closed intermittently just north of Wilshire Boulevard from 7 a.m. to 11 p.m., Monday through Friday, and 8 a.m. to 11 p.m., Saturday and Sunday. Metro is removing the tunneling machines from the Wilshire/Western staging yard and transporting them in dismantled sections to the Wilshire/La Brea staging yard in August and September. Extended 24-hour work hours in the staging yards is expected.
Near Wilshire Boulevard and La Brea Avenue, hauling, deliveries and work on the tunneling machines is occurring. Intermittent lane closures may occur along Wilshire Boulevard between Highland Avenue and Detroit Street. Construction is also occurring at a work zone in the center of Wilshire Boulevard between Sycamore Avenue and Orange Drive to support tunneling. Wilshire Boulevard will be intermittently reduced to one lane between Sycamore and Mansfield avenues.
Excavation, hauling, and subway station construction is also ongoing near Wilshire/Fairfax. Ogden Drive will be intermittently closed at Wilshire Boulevard to support deck panel maintenance and underground investigative work in the Fairfax station area. Anticipated work hours are 7 p.m. to 6 a.m., Monday through Friday.
Utility and tunnel investigation is also occurring near Wilshire/Crescent Heights and Wilshire/La Jolla. Through Friday, Aug. 23, Wilshire Boulevard will be intermittently reduced to fewer than three lanes in each direction between Fairfax Avenue and San Vicente Boulevard to support utility and tunnel investigation work.
Near Wilshire/La Cienega, excavation, hauling, instrumentation and street restoration is ongoing. Excavation continues from the construction staging yards at Wilshire/La Cienega and Wilshire/Gale. Work hours are 6 a.m. to 1 a.m., Monday through Saturday. Hauling hours are anticipated to increase as excavation continues. Intermittent lane reductions, turn restrictions and sidewalk closures may be in place during non-rush hour traffic periods.
In Beverly Hills, a second driveway is being installed at the North Canon staging yard, and work will last through the end of the week. The driveway will be located on Canon Drive near the intersection with Wilshire Boulevard. Work will also include the removal of a street light to accommodate for an ADA-compliant ramp at the crosswalk. The installation will require sidewalk, lane and crosswalk closures.
Work hours are also expected to increase at the La Cienega and Gale staging yards in August and September. Daily construction activities are expected to continue in both staging yards until 1 a.m.
Metro is advising about construction near Wilshire Boulevard and North Canon Drive, where Canon will be turned into a cul de sac north of Wilshire in September. The closure on North Canon Drive is intended to provide a consistent traffic pattern around construction staging areas on Wilshire Boulevard to help mitigate the effects of the work on traffic. The closure will be in place for at least two years.
In Century City, advanced utility work and construction activities are occurring around Avenue of the Stars and Constellation Boulevard.
For questions and concerns, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net or visit metro.net.