Crews are busy at the Wilshire/Western portion of the Purple Line Extension project, where the second of two tunneling machines recently broke through to a construction staging area. (photo courtesy of Metro)
Metro will provide information about Phase 1 of Purple Line Extension work from Wilshire/Western to Wilshire/La Cienega at a meeting on Thursday, July 18, from 6:30 to 7:30 p.m. at SAG-AFTRA, 5757 Wilshire Blvd.
A project overview will be provided, as well as updates about tunneling progress, subway station construction, the business interruption fund and more.
Work is occurring along phases 1 and 2 of the Purple Line Extension project from Wilshire/Western to Century City. Phase 3 will be constructed from Century City to Westwood.
At the east end of the project near Wilshire Boulevard and Western Avenue, westbound Wilshire Boulevard will close to all traffic from Western Avenue to Manhattan Place from midnight to 6 a.m. through July 15. The closure allows components of the tunnel boring machines to be relocated from the Western Avenue construction staging yard to the Wilshire/La Brea staging yard. The twin tunnel boring machines recently completed excavation from La Brea Avenue to Wilshire/Western and parts of the machines will be removed from the ground and reinserted at La Brea Avenue for the next phase of digging toward Beverly Hills.
Westbound traffic will be detoured southbound on Western Avenue to Olympic Boulevard, westbound to La Brea Avenue, and north to Wilshire Boulevard. Parking restrictions will also be posted through July 12 from 6 p.m. to 6 a.m. along sections of Wilshire Boulevard and Manhattan Place.
Near Wilshire Boulevard and La Brea Avenue, deliveries and tunneling support construction continues at staging yards at the intersection, and from a work zone in the middle of Wilshire Boulevard just east of Sycamore Avenue. Intermittent lane closures will be necessary along Wilshire Boulevard and side streets between Highland Avenue and Detroit Street.
Near Wilshire Boulevard and Fairfax Avenue, excavation, hauling and structures work are ongoing. Ogden Drive will be intermittently closed at Wilshire Boulevard to support construction. Instrumentation work, utility work and street maintenance are ongoing near Wilshire and La Cienega Boulevards. Intermittent lane closures and turn restrictions on both streets may be in place during non-rush hour traffic periods.
Hauling and excavation will also continue at the Wilshire/Gale staging yard. Hauling hours are anticipated to increase as excavation progresses. Anticipated work hours are 6 a.m. to 5:30 p.m., and 7 to 10 p.m., Monday through Saturday.
Driveway installation is planned in mid-July at the North Canon Drive staging yard at 9383 to 9393 Wilshire Blvd. and 9395 to 9399 Wilshire Blvd., and at the Reeves Staging Yard, 9430 Wilshire Blvd. The work will last approximately five days and sidewalks will be closed. Intermittent lane closures may also be necessary.
Metro is also setting up a construction staging yard in Century City in the 1900 and 2000 blocks of Century Park East. Sound walls are being erected and preparatory excavation is occurring Monday through Friday from 6 a.m. to 5 p.m. and 7 p.m. to 5 a.m. Advance utility relocation is also occurring in the area.
For questions and concerns, call the 24-hour project hotline at (213)922-6934, email the project team at purplelineext@metro.net or visit metro.net.