The Los Angeles County Metropolitan Transportation Authority is providing updates about construction along Wilshire Boulevard for the Purple Line Extension Project.
At the east end of the project, preparation for pile installation continues near Wilshire Boulevard and Western Avenue, while jet grouting continues near Wilshire Boulevard and Norton Avenue.

(photo courtesy of Metro)
Near Wilshire Boulevard and La Brea Avenue, hauling continues from the staging yard. Additionally, concrete work is occurring at Wilshire Boulevard/Sycamore Avenue from behind the work zone. Concrete work may require intermittent traffic control.
Through Dec. 15, dewatering well maintenance work is also occurring on Wilshire Boulevard between La Brea and Highland avenues, and will involve intermittent traffic control measures. The sidewalk along the south side of Wilshire Boulevard may be closed on Dec. 14 between Sycamore Avenue and Orange Drive. Westbound Wilshire Boulevard will be reduced to one lane between Mansfield Avenue and Orange Drive. Work will take place on the sidewalk on the northeast corner of Wilshire Boulevard/Orange Drive, but sidewalk access will be maintained.
Near Wilshire Boulevard and Fairfax Avenue, excavation, hauling, instrumentation work and deck maintenance is ongoing. Decking preparation, utility work, hauling and dewatering well installation is also occurring near Wilshire and La Cienega Boulevards.
For information, visit metro.net. Members of the public with questions or concerns about Purple Line Extension construction activity can also call the 24-hour project hotline at (213)922-6934, and email the project team at purplelineext@metro.net.