Work continues along Wilshire Boulevard for the Los Angeles County Metropolitan Transportation Authority’s Purple Line Extension project.
Utility relocation work and preparation for pile installation will occur near Wilshire Boulevard and Western Avenue. A work zone will be established on the north side of Wilshire Boulevard between Western Avenue and Manhattan Place.

(photo courtesy of Metro)
Wilshire Boulevard will be reduced to two lanes in each direction between St. Andrews Place and Western Avenue, and left turns will be restricted on Western Avenue for approximately one year. Bus stops will be relocated to Wilshire Boulevard/Serrano Avenue.
This weekend, there will be a full closure of Wilshire Boulevard between Manhattan Place and Western Avenue. It is the third weekend in a series of 14 planned full closures. A detour will be established along Crenshaw Boulevard to Olympic Boulevard to Western Avenue.
Additionally, instrumentation work is ongoing near Wilshire Boulevard and Rossmore Avenue; storm drain repair continues near Wilshire Boulevard and Orange Drive; excavation and hauling is ongoing near Wilshire Boulevard and La Brea Avenue, and median landscaping is occurring near Wilshire Boulevard and Cloverdale Avenue. Excavation and hauling continues near Wilshire Boulevard and Fairfax Avenue, and decking preparation, utility work and hauling is ongoing near Wilshire and La Cienega boulevards.
Metro will hold a community construction meeting on Nov. 16 from 6 to 8 p.m. at John Burroughs High School, 600 S. McCadden Place.
For information, visit metro.net. Members of the public with questions or concerns about Purple Line Extension construction activity can also call the 24-hour project hotline at (213)922-6934, and email the project team at purplelineext@metro.net.