Construction on North Santa Monica Boulevard in Beverly Hills is moving eastward to the final segment of the project. Workers began dismantling the south part of the roadway between Alpine and Doheny drives this week.
Construction on the final segment will be completed in phases, similar to the approach used during the two previous segments. Until the end of December, four lanes of traffic will be open, two in each direction. During this time curbs and gutters will be replaced, and bioswales and raised crosswalks will be built. Starting at the end of December and after the holiday season has ended, the road will be demolished and rebuilt, requiring lane closures and detours. A detour plan similar to the two-lane phase of Segments 1 and 2 will be implemented at that time.
The work and road closures have been scheduled in order to shorten the overall duration of construction, which is now scheduled to be finished in the spring of 2018. The previous schedule was for a completion date in July 2018.
Bus Stops: Buses will continue to travel westbound on North Santa Monica Boulevard with stops at Cañon and Camden drives, and Wilshire Boulevard. Buses travelling eastbound will be diverted onto S. Santa Monica Boulevard in Century City. Buses will stop just west of Charleville Blvd and continue on S. Santa Monica Boulevard with stops west of Camden Drive and west of Crescent Drive. The eastbound buses will return to North Santa Monica Boulevard by way of Doheny Drive.
Turn Restrictions: Left turns are restricted during the construction of this segment. In order to limit vehicles diverting into residential neighborhoods, traffic will be monitored and right turns restrictions could be implemented if necessary.
Intersection Work: Reconstruction of the intersections and construction of raised crosswalks. While this work is underway, intersections will be closed intermittently to both north and south traffic. Notice will be provided ahead of time.
Raised Crosswalks: Raised crosswalks will be built at unlighted intersections on the north side of North Santa Monica Boulevard (Linden, Alpine, Foothill, Elm, Maple, Hillcrest, Arden, Alto and Sierra drives). These striped, high-visibility crosswalks will connect the Beverly Gardens Park jogging/walking path where it pauses at the intersections.
The crosswalks will be constructed at the same level as the curbs, allowing for a safe transition for pedestrians.
An extensive outreach program is underway to inform the community of the North Santa Monica Boulevard Reconstruction progress and how to navigate streets during construction. Watch for mailers, social media messages, newspapers ads and signage.
For information, visit beverlyhills.org/smblvd.










0 Comment