The Los Angeles Transportation Authority has announced that from Friday, July 14 at 9 a.m. through Sunday, July 16 at 6 a.m., decking maintenance work will occur on Wilshire Boulevard near Fairfax Avenue and the work zone on the south side of Wilshire Boulevard will be removed.
When work is completed on July 16, Wilshire Boulevard will be returned to three lanes in each direction, and left turns will return from Wilshire Boulevard to Fairfax Avenue, Orange Grove Avenue and Ogden Drive. To complete the work, westbound Wilshire Boulevard will be reduced to one lane on July 14 from 9 a.m. to 9 p.m. between Spaulding Avenue and San Diego Way. Right turns will be restricted from southbound Fairfax Avenue to westbound Wilshire Boulevard.

Crews continue work near Wilshire Boulevard and La Brea Avenue.
(photo courtesy of Metro)
Additionally, from July 14 at 9 p.m. through July 15 at noon, Wilshire Boulevard will be fully closed between Fairfax Avenue and Crescent Heights Boulevard. Local access to 6100-6300 Wilshire Boulevard will be maintained via northbound Crescent Heights to Wilshire with flagger support at the closure. Local access to Wilshire Boulevard between Crescent Heights and San Vicente Boulevard will be maintained via La Jolla Avenue and southbound Crescent Heights Boulevard. For more information, visit metro.net.Metro also announced that utility relocation work will occur during evening hours along Wilshire Boulevard in Beverly Hills. Work is scheduled on North Gale Drive through Thursday, July 13 and will require the closure of North Gale Drive just north of Wilshire Boulevard. Sidewalks will not be affected.
From July 17 at midnight through July 19 at 6 a.m., pile installation will occur in the intersection of Wilshire and La Cienega boulevards. The construction will involve the drilling and setting of piles, concrete work and street restoration.
For information, visit metro.net, or call the 24-hour project hotline at (213)922-6934.